August 16, 2010

Request for Proposals released

September 7, 2010

First proposals accepted. Proposals submitted by September 7th will be reviewed by October 1

October 1, 2010

First funds granted (estimated)

October 4, 2010

Proposals accepted. Proposals submitted by October 4 will be reviewed by November 5

November 1, 2010

Proposals accepted. Proposals submitted by November 1 will be reviewed by December 3

December 6, 2010

Proposals accepted. Proposals submitted by December 6 will be reviewed by January 7

January 3, 2011

Proposals accepted. Proposals submitted by January 3 will be reviewed by February 4

January 31, 2011

Final proposals accepted. Proposals submitted by January 3 will be reviewed by February 28

February 28, 2011

Final funds granted

April 29, 2011

Completed inventories due to WGBH (Flexible — depending on individual project timelines)

May 31, 2011

Final project and financial reports due to WGBH (Flexible — depending on individual project timelines)